IESO 'Alternative Technologies for Regulation' Procurement (2012)
Ontario's Independent Electricity System Operator (IESO) conducted a procurement for regulation services in 2012, which resulted in the IESO entering into contract with two energy storage facilities, with a total capacity of 6 MW: NRStor's 2MW Minto facility in Wellington County, and Renewable Energy Systems Canada's 4 MW battery storage facility in Strathroy, ON.
This procurement was later followed by the IESO's 50MW storage procurement process that began in 2014.
Posted
Wednesday, November 6, 2019 - 16:24
Last Updated
Wednesday, November 6, 2019 - 16:34
Related Content
Project | Type | Relation(s) | Edit |
---|---|---|---|
NRStor Minto Flywheel Energy Storage Project | Project | Contract | |
RES Amphora | Project | Contract |
Actor | Relation | Edit |
---|---|---|
The Independent Electricity System Operator (IESO) | Lead |